Question: Solution Requirements Utilize Microsoft Excel and / or Word to complete the following steps: 1 . Draw the project network diagram. 2 . Find the

Solution Requirements
Utilize Microsoft Excel and/or Word to complete the following steps:
1. Draw the project network diagram.
2. Find the critical path. Utilize a forward and backward pass analysis. Create a table to display ES, EF, LS, LF, and slack. Calculate the expected project completion time and the standard deviation of the critical path. Use the mean activity time in your calculations.
3. Find the probability of completing in 270 days.
4. Examine the possibility of crashing the project to 250 and 240 days, respectively, to answer the third discussion question. Clarification: use the optimistic time as the crash time you will need to calculate the total cost of crashing using the cost per day. You do not need to calculate cost per day for crashing as with some problems the cost is per day to crash the project down to the optimistic time.
5. Provide recommendations to managers of actions that should be pursued. Share your own insights that you discovered while solving the problem.
Activity
Activity: Predecessor(s):
A: -
B: A
C: A
D: C
E: B
F: E
G: D, F
H: G
I: H
J: H
K: J
L: I, K
TIME ESTIMATE (DAYS)
Activity: Expected Time: Crash Cost/Day
A : 30: 1,500
B: 60: 3,500
C: 65: 4,000
D: 55: 1,900
E: 30: 9,500
F: 0.1: 0
G: 30: 2,500
H: 20: 2,000
I: 30: 2,000
J: 10: 6,000
K: 0.1: 0
L: 30: 4,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!