Question: Solution to Problem 8 . 2 0 from Construction Project Scheduling and Control Book 3 erd Edition by Saleh Mubarak Chapter 8 Time Cost and

Solution to Problem 8.20 from Construction Project Scheduling and Control Book 3erd Edition by Saleh Mubarak Chapter 8 Time Cost and Trade Off. Its an exercise from the book on page 245 exercise number 8.20. Its says: Calculate the normal least-cost and Crash duration for the follwoing project and Calculate the cost associated with each duration. Indirect (overhead ) cost are $100 pwer day