Question: * * SOLUTION: x = 2 . 7 5 ft * * Continuous flow measurement is needed in a long, concrete irrigation canal with a

**SOLUTION: x=2.75 ft** Continuous flow measurement is needed in a long, concrete irrigation canal with a bottom slope of 0.001. The maximum flow rate expected in the 15-ft-wide canal will not exceed the design (normal) depth of 6 ft. Determine the maximum height of a flow measurement weir that keeps the weir backwater from exceeding the 3 ft of freeboard (i.e., a channel depth of 9 ft). Assume the weir friction and velocity head upstream of the weir are negligible.