Question: solve for slack time OC. OD. b. Determine the project's critical path and duration The critical path is A-B-C-F-G-H and the project duration is 26

solve for slack time OC. OD. b. Determine thesolve for slack time

OC. OD. b. Determine the project's critical path and duration The critical path is A-B-C-F-G-H and the project duration is 26 day(s). (Enter your response as a whole number) c. What is the slack for each activity? Activity Time Activity > I Om Enter your answer in the edit fields and then click Check Answer. All parts showing Clear All