Question: Solve How does synchronous manufacturing differ from MRP with respect to scheduling? Multiple Choice O Synchronous manufacturing uses backward scheduling. O Synchronous manufacturing is done
Solve
How does synchronous manufacturing differ from MRP with respect to scheduling? Multiple Choice O Synchronous manufacturing uses backward scheduling. O Synchronous manufacturing is done manually. O Synchronous manufacturing uses forward scheduling. O Synchronous manufacturing uses computers. Synchronous manufacturing is scheduled using days as the time unitStep by Step Solution