Question: Solve problem 1 3 for Chapter 7 section a . What is the project s duration if only normal times are used? The critical path

Solve problem 13 for Chapter 7 section a. What is the project s duration if only normal times are used? The critical path is A-C-E-F and duration is 21 days
The critical path is B-D-E-G and duration is 24 days
The critical path is A-C-E-G-H and duration is 23 days
The critical path is B-C-E-F and duration is 25 days
 Solve problem 13 for Chapter 7 section a. What is the