Question: Solve problem 1 3 for Chapter 7 section a . What is the project s duration if only normal times are used? The critical path
Solve problem for Chapter section a What is the project duration if only normal times are used? The critical path is ACEF and duration is days
The critical path is and duration is days
The critical path is ACEGH and duration is days
The critical path is and duration is days