Question: Solve problem 5-6, assuming that there is a 10% power transmission loss through the network. Pro optimal shipping schedule for *5-6. Three electric power plants
Solve problem 5-6, assuming that there is a 10% power transmission loss through the network.
Pro optimal shipping schedule for *5-6. Three electric power plants with capacities of 25,40, and 30 million kWh supply electricity to three cities. The maximum demands at the three cities are estimated at 30.35, and 25 million kWh. The price per million kWh at the three cities is given in Table 5.25. Problems TABLE 5.25 Price/Million kWh for Problem 5-6 City 2 1 3 1 Plant 2 3 $600 $320 $500 $700 $300 $480 $400 $350 $450