Question: Solve the following Learning Curve problem. Given: Learning rate is 80%. Production was interrupted for two months after unit 8. Production time at 8 th

Solve the following Learning Curve problem.

  • Given:
    1. Learning rate is 80%.
    2. Production was interrupted for two months after unit 8.
    3. Production time at 8th unit was 30 hours.
  • Find
  1. The production time of 9th unit.
  2. The production time of 18th unit.
  3. The cumulative time producing the next batch of 10 units (i.e., 9 through 18)