Question: Solve the following numerical problems. 1. [10 pts] Semple-Brown assembles kitchen tables using bought-in parts of four legs and a top. These have lead times

Solve the following numerical problems. 1. [10
Solve the following numerical problems. 1. [10 pts] Semple-Brown assembles kitchen tables using bought-in parts of four legs and a top. These have lead times of two and three weeks, respectively, and assembly takes a week. The company received orders for 20 tables to be delivered in week 5 of a planning period and 40 tables in week 7 . It has current stocks of 2 complete tables, 40 legs, and 22 tops. When must the company order parts in order to satisfy the orders demanded