Question: Solve the following problems. Clearly justify all your assumptions. Only selected problem ( s ) will be graded. You should attempt all. Problem 1 Estimate

Solve the following problems. Clearly justify all your assumptions. Only selected problem(s) will be graded. You should attempt all.
Problem 1 Estimate the area that would be needed to generate 70MW of power near the city of Tallahassee, Florida. The panels will be placed facing south, with an elevation of 31. The panels efficiency is 20%. Do your estimates:
a. Using NREL's map for global horizontal irradiance.
b. Using TMY data.
 Solve the following problems. Clearly justify all your assumptions. Only selected