Question: A. For the following table of information: i. Draw the network diagram ii. List the network paths iii. Determine the critical path(s) iv. Determine

Table 1 showing a work breakdown schedule for a 5000 sq. Meter school project 

A. For the following table of information: i. Draw the network diagram ii. List the network paths iii. Determine the critical path(s) iv. Determine the float for each activity Prepare a detailed Gantt chart for all activities V. Table 1 showing a work breakdown schedule for a 5000 sq. Meter school project Activity Start Site cleaning Excavation Foundation Columns Walls Floor Roof Plumbing fixtures Finishes Electrical installation/ Equipment Installation Practical completion Duration (Days) 0 18 14 12 14 21 14 12 22 15 32 14 Dependency Start Site cleaning excavation, Foundation Foundation Foundation Columns FLOOR walls Walls Plumbing. Roof Equipment Installation (10 marks) (5 marks) (5 marks) (10 marks) (10 marks) Float

Step by Step Solution

3.46 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

i To make the diagram simpler lets name the activities like below Based on the relations we ca... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!