Question: Solve the linear programming model and make the minimum cost crashing decisions. What is the added cost of meeting the 16-week completion time? Round your
Solve the linear programming model and make the minimum cost crashing decisions. What is the added cost of meeting the 16-week completion time? Round your answers to the nearest dollar. If your answer is zero enter 0.
The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 31 weeks. After viewing this information, management requested overtime be used to complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant:


Develop a complete activity schedule based on the crashed activity times. If your answer is zero enter 0