Question: Solve the problem B B. Find the optimal sequence, which will minimize the mean flow time and also obtain the minimum mean flow time 3

Solve the problem B
B. Find the optimal sequence, which will minimize the mean flow time and also obtain the minimum mean flow time
3 4 Q5. A. Consider the following single machine-scheduling problem with weights: + Job (1) 1 2 Processing time (t) 16 4 5 12 Weight, wi 1 3 2 Determine the sequence, which will minimize the weighted mean flow time of the above problem. Also find the weighted mean flow time. 5 9 3 2 B. Consider the following single machine-scheduling problem. Job (i) 1 2 3 Processing time (t) 15 4 5 4 14 5 8Step by Step Solution