Question: Solve the question fast as sooon & if question was good exlplanation then rating is good! Given the table below: a) Develop the project network
Solve the question fast as sooon & if question was good exlplanation then rating is good! 
Given the table below: a) Develop the project network b) Build the Gantt chart c) Assuming there are only 15 resources available for the duration of this project, how can the schedule be adjusted to level the resources? Revise the Gannt chart to reflect this resource availability. Give solution for excel
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
