Question: Solve the single machine scheduling problem using following data Job Operation Time ( in days ) ABCD AND F 1 5 1 6 Calculate the

Solve the single machine scheduling problem using following data
Job
Operation Time
(in days)
ABCD
AND
F 1516 Calculate the total flow time, maximum completion time and average lateness of the jobs using EDD and SPT.
5
12
21
9
10
Delivery Schedule (in days)
7
16
25
13
12