Question: Solve this problem using the graph Problem 1: Sola Communications has redesigned one of its core business processes. Processing times are not expected to vary
Solve this problem using the graph

Problem 1: Sola Communications has redesigned one of its core business processes. Processing times are not expected to vary significantly, so the management wants to use the line-balancing approach to assign activities to workstations. The process has 11 activities, and the market demand is to process 4 jobs per 400-minute working day. Table 2 shows the standard time and the immediate predecessors for each activity in the process.
First, construct a precedence diagram to help you answer the questions.
Calculate the cycle time corresponding to a market demand of 4 jobs per day (required cycle time).
A) 100
B) 200
C) 300
D) 400
Problem 2: Sola Communications has redesigned one of its core business processes. Processing times are not expected to vary significantly, so the management wants to use the line-balancing approach to assign activities to workstations. The process has 11 activities, and the market demand is to process 4 jobs per 400-minute working day. Table 2 shows the standard time and the immediate predecessors for each activity in the process.
First, construct a precedence diagram to help you answer the questions.
What is the actual minimum number of workstations?
A) 5
B) 4
C) 3
D) 2
Problem 3: Use the longest activity time rule as the primary rule to balance the line.
What is the efficiency of the line?
A) 86%
B) 79%
C) 61%
D) 925