Question: Solve this two questions: 1) From the activity list below, determine: a) (3 marks) What activities lie on Critical Path (Network diagram is not needed

Solve this two questions: 1) From the activity list below, determine:

a) (3 marks) What activities lie on Critical Path (Network diagram is not needed for submission)

b) (2 marks) What is the duration of Critical Path (in months)

Solve this two questions: 1) From the activity list below, determine:a) (3marks) What activities lie on Critical Path (Network diagram is not needed

From the activity list below, determine: a) (3 marks) What activities lie on Critical Path (Network diagram is not needed for submission) b) (2 marks) What is the duration of Critical Path (in months) Activity Predecessor(s) | Duration A Product Design 5 B Market Research 1 C Production Analysis 5 D Product model 5 E Sales brochure 7 F Cost analysis 2 G 8 H 3 I 2 J 2 From the network diagram shown below, determine: a) (1 marks) The earliest start (ES) of Task C b) (1 marks) The latest start (LS) of Task E c) (2 marks) The Critical Path d) (2 marks) The duration of the Critical Path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!