Question: solve with explanation please. & (15 points) Apply the critical-path scheduling algorithm with two machines to determ priority hd for the order requirement digraph below

solve with explanation please. 
& (15 points) Apply the critical-path scheduling algorithm with two machines to  

& (15 points) Apply the critical-path scheduling algorithm with two machines to determ priority hd for the order requirement digraph below and determine the time it will take to complete all the tasks. You must show all your work for Ending the list you use. n T. Machine 1 Maction 2 T 012 T Ts 7 4 3 5678919 11 12 13 14 15 16 17 18 19 20 21 22 23 24 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24