Question: Solvr Question 8 Using the diagram below, what is the cost of the foundation? 1.1. Foundation 1.1.1. Dig Foundation Duration 32 hrs Remaining Cost $2560.00

Solvr

Question 8 Using the diagram below, what is the cost of the foundation? 1.1. Foundation 1.1.1. Dig Foundation Duration 32 hrs Remaining Cost $2560.00 1.1.2. Install Rebar Duration 8 hrs Remaining Cost $780.00 1.1.3. Pour Concrete Duration 24 hrs Remaining Cost $2000.00 $2780 $4560 $5340 $2000 D Question 9 You can be both accountable and responsible for a task outlined in a RACI chart