Question: someone keeps posting wrong and totally unrelated content. Please if you can actually help let me know how to solve the question. Thank you. The
someone keeps posting wrong and totally unrelated content. Please if you can actually help let me know how to solve the question. Thank you.
The following table is a list of activities in the construction of a pump station.
Create a network diagram based on these activities. Pls use excel to produce
your diagram as we have done in the class. You must show formulas and
dependencies using arrows and use the network diagram legend provided
below. You must also showhighlight the critical path in the network diagram.
Conduct a forward and backward pass and identify the early starts ES early
finishes EF late starts LS late finishes LF and floats TF for all activities.
Pls also include a network table to show all the data generated. Use the table
below but add additional columns for ES EF LS LF and TF for all the activities
You may assume the start date is day
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock