Question: Source: Project Management I need help with questions #9 and #10. Please screenshot of the diagrams and table. Thank you. #9 Question 10 i5 pts
Source: Project Management
I need help with questions #9 and #10. Please screenshot of the diagrams and table. Thank you.
#9



Question 10 i5 pts This question has three parts. Please answer ill parts (a. b. and cl in the same textbox below and label each section appropriately with the corresponding letter la, b, and c). Consider a class project with the following 7 activities given below that you are working on along with Alice and Bob. Alice is in the same class as you, while Bob is in the other section of project management. 50 you meet Alice very frequently, but most of your (and Alice's) interaction with Bob is through emails. Bob, given his other commitments, can only be assigned two activities for this class project. You are thinking of allocating F and G to Bob. and splitting the remaining 5 activities (A thru E] between yourself and Alice. Activity Depends on A C, E B F C D, E D C, B, G E A. C F B G A, D h The table above states that acvityA is dependent on activityC and El A B C D I'DUOEDP a. Fill out the table below with the DSM corresponding to these activities (5 pts). IA hand-drawn table is acceptable You can also insert a table into the textbox by clicking "Insert -> Table", Same for part (c)] A C, E CO F D. E O C, B, G m A, C B G A, D [The table above states that activity A is dependent on activity C and E.] a. Fill out the table below with the DSM corresponding to these activities. (5 pts). [A hand-drawn table is acceptable. You can also insert a table into the textbox by clicking "Insert -> Table". Same for part (c)] A B C D E F G A B C D E F G b. Is this assignment of activities to the team appropriate? Why or why not? (5 pts). c. Which 2 activities would you recommend be assigned to Bob? Draw the DSM corresponding to your assignment below [Assume that Bob can do 2 of the 7 activities] (5 pts). Edit View Insert Format Tools Table 12pt w Paragraph B I U A v Q V TV V v v DV S. EVEVEVD Question 9 30 pts This question has four parts. Please answer all parts (a, b, c, and d) in the same textbox below and label each section appropriately with the corresponding letter (a, b, c, and d). Consider the project given below. Activity Dependencies Duration (weeks) A (START) 3 B A 3 C A 3 D A 2 E B, C 3 D 2 G B, F 4 H (END) E, G 6 a. Draw the network diagram and indicate the early/late start/end times for all the activities. (5 pts + 10 pts). [A hand-drawn diagram is acceptable and recommended to save your time. If you need to insert an image of a diagram, please click "Insert" and then select "Image"!] b. What is the critical path (5 pts). c. If activity B was uncertain in duration, and could be 1 week or 5 weeks with equal likelihood, what is the average time taken to finish the project? (5 pts). d. When activity B is uncertain (as above), when should you schedule the start time of activity E? (5 pts). Edit View Insert Format Tools Table 12pt v Paragraph BIYA & T V PV LV OV DV S. SV EV EV
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
