Question: Space Module Assembly. An aerospace company has received a contract from NASA for the final assembly of a space module for an upcoming mission. A

Space Module Assembly. An aerospace company has received a contract from NASA for the final assembly of a space module for an upcoming mission. A team of engineers has determined the activities, precedence constraints, and time estimates as given in Table 9.19.
TABLE 9.19
ActivitySymbolImmediate predecessorsTime estimate (days)Construct shell of moduleA30Order life support system and scientific experimentation package from same supplierB15Order components of control and navigational systemC25Wire moduleDA3Assemble control and navigational systemEC7Preliminary test of life support systemFB1Install life support in moduleGD, F5Install scientific experimentation package in moduleHD, F2Preliminary test of control and navigational systemIE, F4Install control and navigational system in moduleJH, I10Final testing and debuggingKG, J8
a.Draw the AOA network for this project. (Hint: You should have 10 events and two dummy activities.)
b.Calculate total slacks and free slacks, and interpret their meaning.
c.Determine the critical path and interpret its meaning.
d.Construct a Gantt chart and identify scheduling flexibilities.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!