Question: Speakers: Lead time = 1 week; Minimum order quantity = 5000. Level 1, 2 speakers per unit. Week 1 2 3 4 5 6 Gross

Speakers: Lead time = 1 week; Minimum order quantity = 5000. Level 1, 2 speakers per unit.

Week

1

2

3

4

5

6

Gross Requirements

Scheduled Receipts

5000

Projected Ending Inventory: 0

Net Requirements

Planned Receipts

Planned Orders