Question: Spring, 2 0 2 4 Both will be penalized if two exams are exactly identical. EXAM # 1 I You are required to show the

Spring, 2024 Both will be penalized if two exams are exactly identical.
EXAM #1I You are required to show the process to get your final answer.
You will not earn any credit with the final answer only.
Bill Fennema, President of Fennema Hospitality, has developed the activities, durations, and
predecessor relationships in the following table for building new motels.
Time (Days)
Activity Immediate Predecessor a m b ECT VAR
A none 8111411.001.00
B A,F 4122112.178.03
C none 5696.330.44
D C,F 410119.171.36
E B,D 7797.330.11
F none 49118.501.36
G D 58107.830.69
H E,G 11121412.170.25
I G 5797.000.44
J E 4565.000.11
K H,I,J 9111311.000.44
Q1. Draw the AON network.
Q2. Find the critical path.
Q3. How many days are required to complete the project?
Q4. What are the ES and EF of Activity I? ES= EF=
Q5. What are the LS and LF of Activity D? LS= LF=
Q6. What is the probability of completing the project in 50 days?
Q7. What is the probability of completing the project in 57 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!