Question: SPT sequence drop downs ranges from 1 to 6. Last drop down answer choices: The SPT Rule / Numerical Order Thanks. The following six jobs

SPT sequence drop downs ranges from 1 to 6.
Last drop down answer choices: The SPT Rule / Numerical Order
Thanks.
The following six jobs are to be scheduled on a single machine: (mn.) Makespan: minutes Average flow time: minutes b. In what order would the jobs be processed using the SPT rule? The SPT sequence is Compute the average flow time after each job is completed. Round your answer to the nearest whole number. Average flow time: minutes Compare this answer with your answer to part a. The minimizes flow time and gets the most work done in the least amount of timeStep by Step Solution