Question: ssuming that a project being considered has normal cash flows, with one outflow followed by a series of inflows, which of the following statements is
ssuming that a project being considered has normal cash flows, with one outflow followed by a series of inflows, which of the following statements is accurate? If a project has normal cash flows and its IRR exceeds its WACC, then the project's NPV must be positive. If Project A has a higher IRR than Project B, then Project A must also have a higher NPV. The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business. The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC. If Project A has a higher IRR than Project B, then Project A must have the lower NPV
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
