Question: Stadium Construction Project Problem: If F takes four days instead of two, what is the critical path of the project? table [ [ ACTIVITY

Stadium Construction Project Problem: If F takes four days instead of two, what is the critical path of the project?
\table[[ACTIVITY IMMEDIATE PREDECESSOR,DURATION (days),],[A,-,1],[B,A,4],[C,A,3],[D,A,7],[E,B,6],[F,C,D,2],[G,E,F,7],[H,D,9],[I,G,H,4]]
ACFGI
ADFGI
ADHI
ACEGI
ABEGI