Question: Stadium Construction Project Problem: What is the project duration? table [ [ ACTIVITY , MMEDIATE PREDECESSOR,DURATION ( days ) ] , [ A ,

Stadium Construction Project Problem: What is the project duration?
\table[[ACTIVITY,MMEDIATE PREDECESSOR,DURATION (days)],[A,A,1],[B,A,4],[C,A,3],[D,B,7],[E,C,D,6],[F,E,F,2],[G,D,7 A],[H,,9]]
23 days
24 days
20 days
22 days
21 days
 Stadium Construction Project Problem: What is the project duration? \table[[ACTIVITY,MMEDIATE PREDECESSOR,DURATION