Question: standard against which the project performance is measured. table [ [ Work Packages,W 1 , W 2 , W 3 , W 4 ,

standard against which the project performance is measured.
\table[[Work Packages,W1,W2,W3,W4,W5,W6],[A,10,5,8,,,],[B,,,,9,,],[C,,,,,2,2],[Total,10,5,8,9,2,2]]
You are analyzing the project performance at the end of Week 3. Activity "A" is 60% complete and its actual cost is 9. Activities B and C have not started yet.
What is the to-complete performance index of this project?
Use two decimal places in your calculations.
 standard against which the project performance is measured. \table[[Work Packages,W1,W2,W3,W4,W5,W6],[A,10,5,8,,,],[B,,,,9,,],[C,,,,,2,2],[Total,10,5,8,9,2,2]] You