Question: Standard work sheets are required for standard operations. Which element is included on the sheets? Cycle time based on takt time Short-cut work sequences Maximized
- Standard work sheets are required for standard operations. Which element is included on the sheets?
- Cycle time based on takt time
- Short-cut work sequences
- Maximized inventories
- The annual or semi-annual review dates