Question: Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and
Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Time Immediate Task (sec) Predecessor A 12 B 14 A 8 A 5 B, C E 20 D Rosenberg's goal is to produce 175 PDAs per hour. a) The cycle time for the production of a PDA = seconds (round your response to two decimal places). b) The theoretical minimum number of workstations that Rosenberg can achieve in this assembly line = (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Tasks Assigned to Workstation Workstation # 1 A umber). =) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # 1 2 Tasks Assigned to Workstation A B 3 Were you able to assign all the tasks to the theoretical minimum number of workstations? mumber). C c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum E activity assignment s Workstation # 1 Tasks Assigned to Work D A 2 3 B Were you able to assign all the tasks to the theoretical minimum number of workstations? Workstation # 1 Tasks Assigned A No 2 B 3 Yes Were you able to assign all the tasks to the theoretical minimum number of workstations? n a
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts