Question: Star Construction Corp. has a contract to construct a building for $ 1 0 , 8 7 6 , 0 0 0 . The building

Star Construction Corp. has a contract to construct a building for $10,876,000. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,801,600. Construction commenced on 4 February 205. Actual costs were in line with estimated costs for 205 and 206. In 20X7, actual costs exceeded estimated costs by $138,400.
Total construction costs incurred in each year were as follows:
\table[[205,$2,682,000
 Star Construction Corp. has a contract to construct a building for