Question: Star Construction Corporation has a contract to construct a building for $ 1 0 , 9 5 0 , 0 0 0 . The building

Star Construction Corporation has a contract to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,850,000. Construction commenced on 4 February 205. Actual costs were in line with estimated costs for 205 and 206. In 207, actual costs exceeded estimated costs by $150,000.
Total construction costs incurred in each year were as follows:
20X5: $2,700,000
20X6: $4,500,000
20X7: $1,800,000
Progress billings based on the amount of work completed were collected each year. Star Construction uses the percentage-of-completion method. The percentage-of-completion is based on costs incurred compared with estimated total costs of the project.
Company also billed the client and collected the following payments
Year
Billings
Payments Received
20X5:
$2,300,000
$2,100,000
20X6:
$4,900,000
$4,700,000
20X7:
$3,750,000
$4,150,000
Required: (12 Marks) Calculate Net income for the construction project for each of the three years:
a) Completed contract method?
20X5: $______________20X6: $__________________20X7____________________.
b) Percentage-of-completion method? (basis: estimated costs to complete)
20X5: $______________20X6: $__________________20X7____________________.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!