Question: Star Construction Corporation has a contract to construct a building for $ 1 0 , 9 5 0 , 0 0 0 . The building
Star Construction Corporation has a contract to construct a building for $ The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $ Construction commenced on February Actual costs were in line with estimated costs for and In actual costs exceeded estimated costs by $
Total construction costs incurred in each year were as follows:
X: $
X: $
X: $
Progress billings based on the amount of work completed were collected each year. Star Construction uses the percentageofcompletion method. The percentageofcompletion is based on costs incurred compared with estimated total costs of the project.
Company also billed the client and collected the following payments
Year
Billings
Payments Received
X:
$
$
X:
$
$
X:
$
$
Required: Marks Calculate Net income for the construction project for each of the three years:
a Completed contract method?
X: $X: $X
b Percentageofcompletion method? basis: estimated costs to complete
X: $X: $X
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock