Question: Start dates in the following network logic diagram are defined as early morning, finish dates are evening If tasks are scheduled to begin at early
Start dates in the following network logic diagram are defined as early morning, finish dates are evening If tasks are scheduled to begin at early start date, what is true? Day 16 - Day 21 Activity B Day 26 - Day 31 Day 1 - Day 15 Activity A Day 2 - Day 16 Day 31 - Day 60 Activity D Day 32 - Day 61 Day 16 - Day 30 Activity C Day 17 - Day 31 Activity A has a free float of 11 d Activity B has a total float of 10 d Activity A has a total float of 10 d Activity B has a free float of 11 d