Question: Starting with original lab 4 data, which path ( s ) is / are the critical path ( s ) if activities B and D

Starting with original lab 4 data, which path(s) is/are the critical path(s) if activities B and D increase by 2 days, while activity H decreases by 1 day?
Question 1Select one or more:
a.
A-C-E-H-I
b.
A-C-E-F
c.
B-C-E-H-I
d.
B-C-E-F
e.
B-D-E-H-I
f.
B-D-E-F
g.
B-D-G