Question: Statement of Work [ Describe the Work Breakdown Structure (WBS), primary tasks, and the schedule and order they need to occur] Step 1: Buying Land

Statement of Work

[ Describe the Work Breakdown Structure (WBS), primary tasks, and the schedule and order they need to occur]

Step 1: Buying Land

1. Frontage on County road

2. Land Survey

3. Title Search

4. Title Insurance

5. Water Table for Well

6. Septic System Soil Test

7. Solar Heat

8. Land Improvement

Step 2: Before Closing

9. Review Loan Documents

10. Prepare Specifications Sheet

11. Prepare complete Materials/ Labor Cost Estimates

12. Submit Loan Application

13. Sewer Tap (or Septic System Permit)

14. Building Permit

15. Construction Loan Closing

Step 3: After Closing

16. Building License required?

17. Compliance Bond required?

18. Water Tap & Meter (or contact Well Digger)

19. Order Temporary Services

Electricity

Water

20. Prepare Site Plan

Step 4: Subcontractors

21. Check References

22. Are they Bonded?

23. Are they Licensed?

24. Guarantee their work?

25. If Guaranteed, How Long?

26. Liability Insurance

27. Workmans Compensation Insurance

28. Who do Better Builders Use?

29. Get Written Estimates

30. Check Low Bidders quality

Step 5: Buying Materials

31. Select 3 reputable Building Supply firms

32. Submit Material Estimates to each

33. Check supply house Bid against original estimates

and correct difference

34. Select Building Supply firm with best combination

of Service, Terms and Price

Step 6: Site & Foundation

35. Review Step 3, then do Rough Grading

36. Cut Driveway

37. Put 4-6 Gravel on Driveway

38. Get Water Meter (or Dig Well)

39. Clear Home Site, plus 10 15 Work Area

40. Install Temporary Power Pole

41. Crawl Space or Basement

Batter Boards

Dig Foundation Footings

Pour Footings

Lay Block or Pour Walls

42. Pre-Treat for termites

43. Waterproof/Backfill

44. Slab and Garage

Form Boards

Plumbing

Miscellaneous Pipes

Gravel

Polyethylene vapor barrier

Pre-Wire (landscape)

Pour Concrete

45. Spot Foundation Survey

46. Gas, Sewer & Miscellaneous Utility lines(If needed)

Step 7: Framing

47. Buy Building Level

48. Check Foundation Level/ Square

49. Check Level/ Square Again

50. Have Framing Materials Delivered

51. Maintain Materials Supply

52. Cull Materials

53. Basement Walls & Beams

54. Subfloor, 1st Floor

55. Set Special Tubs, 1

st Floor

56. Walls/ Partitions, 1

st Floor

57. Subfloor, 2nd Floor

58. Set Special Tub, 2nd Floor

59. Walls/ Partitions, 2nd Floor

60. Wall Sheathing

61. Check Level, Square & Layout as work progresses

62. Ceiling Joists

63. Rafters & Trusses

64. Roof Sheathing and Felt

65. Framing Inspection

66. Install Doors/Windows

67. Measure Cabinets.

68.Solar panels

69.Wind tribune

70. Install batteries and Inverter

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!