Question: Statement: True or False? a . The main difference between job order and process costing systems is the amount of detail captured for each product.
Statement:
True or False?
a
The main difference between job order and process costing systems is the amount of detail captured for each product.
b
Most companies apply indirect costs overhead based on direct materials because materials are tangible and visible.
c
Overallocated overhead occurs when the actual overhead is less than the estimated overhead.
d
If a company wants accurate job records, the company will insist on recording actual direct materials, actual direct labor, and actual overhead costs.
e
Companies frequently use a normal cost system for simplicity, to smooth out the effects of seasonal fluctuations, and so that each job can be allocated a representative amount of indirect costs as the job is produced. Otherwise, a company could not assign actual correct indirect costs until the end of the period because overhead costs such as rent are spent in groups and are not individually traceable to a given job.
f
If the difference between allocated overhead and actual overhead is small, the difference is usually recorded as an adjustment of cost of goods sold rather than spread over all the jobs in the work in process, finished goods, and cost of goods sold accounts.
g
The work in process account is a temporary expense account that is reported on the income profitloss statement.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock