Question: Station 1 Machine A 30 min/unit Station 2 Station 3 Station 1 Machine B 14 min/unit 5 min/unit 30 min/unit A three station work

Station 1 Machine A 30 min/unit Station 2 Station 3 Station 1

Station 1 Machine A 30 min/unit Station 2 Station 3 Station 1 Machine B 14 min/unit 5 min/unit 30 min/unit A three station work cell is illustrated in the image above. A unit needs to be processed at either Machine A or Machine B for Station 1 (parallel lines, both lines doing the exact same thing). The unit is then processed at Stations 2 and 3 before leaving the work cell. The process time of each machine/station is indicated in the flowchart. Specify the bottleneck(s).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock