Question: Stefan is a project manager and is trying to identify the longest activity sequence of his project to determine the shortest possible duration to complete

Stefan is a project manager and is trying to identify the longest activity sequence of his project to determine the shortest possible duration to complete the project. Stefan is looking for the ____________.
Group of answer choices
Business Case
Scope Statement
Critical Chain
Critical Path