Question: Step 3: The Project Using your new methodology, SCC would like you and you to complete the following project: Scope: The scope of the project

Step 3: The Project

Using your new methodology, SCC would like you and you to complete the following project:

Scope: The scope of the project consists of 9 applications

Initial Development Cost (YR 0) Year 1 Income Year 2 Income Year 3 Income Year 4 Income Year 5 Income
Application 1 $ 350,000.00 $ 65,000.00 $ 74,750.00 $ 89,700.00 $ 94,185.00 $ 95,126.85
Application 2 $ 275,000.00 $ 52,000.00 $ 62,400.00 $ 68,640.00 $ 70,012.80 $ 71,413.06
Application 3 $ 500,000.00 $ 65,000.00 $ 79,300.00 $ 83,265.00 $ 89,926.20 $ 94,422.51
Application 4 $ 450,000.00 $ 50,000.00 $ 65,000.00 $ 69,550.00 $ 73,723.00 $ 77,409.15
Application 5 $ 300,000.00 $ 130,000.00 $ 143,000.00 $ 145,860.00 $ 160,446.00 $ 170,072.76
Application 6 $ 450,000.00 $ 82,000.00 $ 94,300.00 $ 95,243.00 $ 96,195.43 $ 100,043.25
Application 7 $ 750,000.00 $ 230,000.00 $ 287,500.00 $ 301,875.00 $ 316,968.75 $ 323,308.13
Application 8 $ 550,000.00 $ 75,000.00 $ 91,500.00 $ 93,330.00 $ 100,796.40 $ 103,820.29
Application 9 $ 250,000.00 $ 65,000.00 $ 85,800.00 $ 88,374.00 $ 93,676.44 $ 95,549.97

Given the critical nature of the project, the company has developed a high-level budget and potential income for each application.

  • Year 0 is the projected cost the company has estimated for the build of the component. This includes a 15% overhead cost for project management work
  • Year 1-Year 5 is the amount of revenue the company has estimated for the product
  • The Acceptable Rate of Return for all projects with the company is 10%

Step 4: Manage a project

  • Describe the process that your team will use to elicit and decompose the requirements for the project
  • Develop a Project Overview Statement document for the project
  • Create a WBS for the project. Remember your WBS is a deliverable base, so there should be a section of your WBS which outlines our project management deliverables
  • Using the following information develop a Gantt chart
    Optimistic Estimate Pessimistic Estimate Most Likely Estimate
    Application 1 4 months 9 months 6 months
    Application 2 1 month 5 months 3 months
    Application 3 5 months 10 months 7 months
    Application 4 1 month 7 months 4 months
    Application 5 5 months 10 months 8 months
    Application 6 2 months 9 months 5 months
    Application 7 5 months 12 months 7 months
    Application 8 3 months 13 months 9 months
    Application 9 4 months 11 months 8 months
  • Describe strategies you can use to bring the project timeline to 12 months.
  • Develop a team agreement
  • Using your defined prioritization process, prioritize each application.
  • Using the defined organizational structure, create a pictorial and narrative description of the organizational structure for the project.
  • Identify at least ten potential stakeholders for your project.
  • Identify at least five risks to include both threats and opportunities associated with the project. For each risk, please include the following information:
    • Category
    • Impact
    • Probability
    • Description of the risk
    • Mitigation Strategy
  • Describe the process your team can use to determine if the projects are making the appropriate revenue.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!