Question: step a = 7 minutes , Step B = 3 minutes, Step C 10 minutes, Step D = 6 minutes, Step E = 5 minutes

step a = 7 minutes , Step B = 3 minutes, Step C 10 minutes, Step D = 6 minutes, Step E = 5 minutes . What is the utilization of the process? What is the capacity of the process over an 8 hour period? What is the utilization of step A? If you had a total of 11 workers to split amongst the 5 tasks in an effort to maximize the capacity, what is the utilization of Step C if each person can work only one of the tasks? If you could add one more resource to one of the steps (assuming each step is currently being done by an individual resource), what is the maximum hourly capacity you can achieve?