Question: Step Description Time per computer 1 Move the machine to their work area 4 . 9 minutes 2 Scrub and clean hardware 1 2 .

Step
Description
Time per computer
1
Move the machine to their work area
4.9 minutes
2
Scrub and clean hardware
12.1 minutes
3
Strip off old operating system
6.9 minutes
4
Install new operating system & software
10 minutes
5
Move machine back to its previous location
9 minutes
One member of ITS will be assigned to each step. Each member will work a 40 hours per week and rotate jobs each week. Demand is forecasted at having to refurbish 246 computers per week. ITS is unsure that they can deliver on the promise.
After 8 hours, how many units of work-in-process (WIP) will be at station 2(or think of it as between station 1 and 2) if all stations are working at their maximum capacity (assume steady state)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!