Question: Step Setup Time Process Time Per Unit 3 minutes B 3 minutes 3 minutes 3 minutes per unit 4 minutes per unit 2 minutes per

Step Setup Time Process Time Per Unit 3 minutes B
Step Setup Time Process Time Per Unit 3 minutes B 3 minutes 3 minutes 3 minutes per unit 4 minutes per unit 2 minutes per unit 10 minutes per unit 3 minutes per unit D 2 minutes E 2 minutes If the standard batch size is 46, how many minutes does lead time decrease by cutting the batch size in half? (NOTE: Please round down to the nearest whole part when halving the batch size.)