Question: Strauss Company established a predetermined variable overhead cost rate at $10.30 per direct labor hour. The actual variable overhead cost rate was $9.30 per hour.
| Strauss Company established a predetermined variable overhead cost rate at $10.30 per direct labor hour. The actual variable overhead cost rate was $9.30 per hour. The planned level of labor activity was 74,100 hours of labor. The company actually used 79,200 hours of labor. |
| Required: |
| a. | Determine the total flexible budget variable overhead cost variance |