Question: stuck on this... Question 7 (1 point) At the Nimble Digits Division of Block C Enterprises the assembly of unit 6 of one particular system

stuck on this... stuck on this... Question 7 (1 point) At the
Question 7 (1 point) At the Nimble Digits Division of Block C Enterprises the assembly of unit 6 of one particular system required 48 hours. The average learning rate for Nimble Digits is 85%. Determine the average hours required to produce twenty unit in this series 43.3 hours 49.1 hours 52.9 hours 56.6 hours 60.4 hours 64.2 hours 68.0 hours O71.7 hours