Question: Student name: _ _ _ _ _ _ _ _ _ _ TRUE / FALSE - Write ' T ' if the statement is true

Student name:__________
TRUE/FALSE - Write 'T' if the statement is true and 'F' if the statement is false.
1) While organization culture is important to the overall function of an organization, it has minor influence on its project management.
true
false
2) In the projectized form of project management structure, there is limited technological expertise when compared to the functional or matrix organization.
true
false
3) The matrix form of project management is notable for the tension it creates between functional managers and project managers who both bring critical expertise and perspectives to the project.
true
false
MULTIPLE CHOICE - Choose the one alternative that best completes the statement or answers the question.
4) The arrangement that manages projects within the existing organizational structure is __________ organization.
A) functional
B) balanced matrix
C) weak matrix
D) strong matrix
E) projectized
5) Which of the following is an advantage of a functional project management organization?
A) Maximum flexibility in the use of staff
B) Good integration across functional units
C) Shorter project duration
D) Strong motivation of project team members
E) Longer project duration
6) A project team that operates with a full-time project manager as a separate unit from the rest of the organization is structured using ________ organization.
A) functional
B) balanced matrix
C) weak matrix
D) strong matrix
E) projectized
7) All of the following are organizational considerations when determining the right project management structure EXCEPT
A) how important project management is to the success of the organization.
B) what percentage of core work involves projects.
C) resource availability.
D) assess current practices and determine any changes that are needed to more effectively manage projects.
E) budget constraints.
8) In which of the following is the balance of authority strongly in favor of the functional managers?
A) Weak matrix
B) Balanced matrix
C) Strong matrix
D) Matrix
E) Neutral matrix
9) Which structure would be most appropriate for developing a new, highly innovative product that has strict time constraints?
A) Functional organization
B) Balanced matrix
C) Dedicated project team
D) Strong matrix
E) Weak matrix
10) Which of the following cultural characteristics relates to the degree to which employees identify with the organization as a whole rather than with their type of job or field of professional expertise?
A) Member identity
B) Team emphasis
C) Managerial focus
D) Unit integration
E) Control
11) No radical alteration in the design or operation of the parent organization is a major advantage of __________ organization.
A) projectized
B) dedicated project team
C) weak matrix
D) strong matrix
E) functional
12) A high level of motivation and the tendency for projects to get done more quickly are benefits of using the ________ organizational approach to project management.
A) dedicated project team
B) weak matrix
C) strong matrix
D) functional
E) projectized
13) The cultural characteristic that refers to the degree to which the organization monitors and responds to changes in the external environment is known as ___________.
A) open-systems focus
B) team emphasis
C) conflict tolerance
D) unit integration
E) reward criteria
14) Which of the following PMO types would address questions like How are our projects progressing? Which ones are on track? Which ones are not? How are we doing in terms of cost? Which projects are over budget?
A) Weather station.
B)911 call center.
C) Control tower.
D) Resource pool.
E) Command and control center.
15) An indicator of project success within an organization is the strength of the ______ to support the project management structure.
A) project manager
B) program
C) firm
D) organization culture
E) top management
16) If a manager faces a programmed decision, that means
A) a clear structure or procedure exists for arriving at the right decision.
B) the decision maker has no predetermined structure on which to rely.
C) there are unlimited possible solutions, each of which has merits or drawbacks.
D) the decision maker should be creative in choosing what to do.
E) the decision most likely carries substantial risk.
17) When a solution is specifically designed for a particular problem or set of problems, it is referred to as
A) groupthink.
B) a programmed decision.
C) a ready-made solution.
D) a contingency plan.
E) a custom-made solution.
18) Managers who optimize their decisions will attempt to
A) choose the first, minima

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!