Question: Study: Accelerating Drywall Installation in the Metro Office Complex Project After a Delay Background The Metro Office Complex Project involves constructing a large commercial building

Study: Accelerating Drywall Installation in the Metro Office Complex Project After a
Delay
Background
The Metro Office Complex Project involves constructing a large commercial building that has
encountered significant delays in the drywall installation phase. These delays are attributed to
supply chain disruptions and an unexpected shortage of skilled labor, putting the project's overall
timeline at risk. The project management team is tasked with developing a strategy to accelerate
the drywall phase to recover lost time without compromising safety or work quality.
Objective
To quantitatively analyze the impact of the delays on the drywall installation phase, propose
multiple recovery strategies, and calculate the additional costs and time required to implement
these strategies efficiently.
Assumptions and Data Provided
Total Drywall Area: 200,000 sq. ft.
Drywall Crews: 4, each originally expected to install 800 sq. ft. of drywall per day.
Original Timeline for Drywall Work: 90 days.
Delay Duration: 10 days.
Labor Hours Available per Day per Crew: 8 hours, 5 workers per crew.
Cost of Labor per Hour per Worker: $25 regular, $37.50 overtime (1.5x regular rate).
Cost of Hiring an Additional Crew (Including Training): $7,000.
Investment in Automated Drywall Tools per Crew: $15,000.
Daily Productivity Increase with Automated Tools: 25%.
Average Cost of Drywall Materials per sq. ft.: $2.
Estimated Cost Increase for Expedited Drywall Delivery: 15%.
Tasks:
1. Quantitative Impact Assessment:
Calculate the financial impact of the 10-day delay, including lost labor productivity and
increased material costs.
2. Recovery Plan Development & Cost-Time Calculation:
Option 1: Overtime Work: Assess the additional hours and labor costs needed to catch up
within the revised timeline.
Option 2: Hiring Additional Crews: Evaluate the cost-effectiveness and timeline impact
of adding more crews.
Option 3: Investing in Technology: Calculate the cost and timeline benefits of adopting
automated drywall tools.
3. Risk Management and Quality Control:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!