Question: [Study guide - final exam] If daily demand is constant at 11 units per day, and lead time averages 12 days with a standard deviation
[Study guide - final exam] If daily demand is constant at 11 units per day, and lead time averages 12 days with a standard deviation of 3 days, 95 percent service requires how much safety stock? 72 units 34 units 49 units 28 units 54 units