Question: Study the activity list and its network diagram. Calculate the early start, early finish, late start and late finish of activity C. a. ES=2,EF=5,LS=6,LF=8 b.

Study the activity list and its network diagram. Calculate the early start, early finish, late start and late finish of activity C. a. ES=2,EF=5,LS=6,LF=8 b. ES=3,EF=5,LS=6,LF=8 c. ES=2,EF=5,LS=6,LF=6 d. ES=5,EF=3,LS=6,LF=8 Study the activity list and its network diagram. Calculate the early start, early finish, late start and late finish of activity C. a. ES=2,EF=5,LS=6,LF=8 b. ES=3,EF=5,LS=6,LF=8 c. ES=2,EF=5,LS=6,LF=6 d. ES=5,EF=3,LS=6,LF=8