Question: Study the following project - spending plan in Question 2 and calculate the following ( indicate the actual calculations in full ) : 1 .

Study the following project-spending plan in Question 2 and calculate the following (indicate the
actual calculations in full):
1. Cash Flow for Task b
2. Total BCWP
3. CVAR/CV for Task a
4. BCWP - ACWP for Task c
5. BCWP for Task d
6. Total ACWP
7. Total CVAR/CV
8. Total BCWP Total cash flow
QUESTION 2
Re-draw the project spending plan and fill-in the missing values.
PROJECT SPENDING PLAN
PROJECT NAME : HOSTING OF THE LAUNCH OF A COMMUNITY
CITIZEN PARTICIPATION FORUM IN CARLETONVILLE
FROM 1014 JUNE 2024
START DATE : 3 MARCH 2024
PROJECT DURATION : 5 MONTHS
CURRENT DATE : 3 FEBRUARY 2024
CURRENT PROJECT BUDGET : R300000
ACTIVITY/TAS
K
COMPLETIO
N DATE
SCHEDULE
D
BUDGETE
D AMOUNT
(BCWP)
CASH
FLOW
ACTUAL
COST
(ACWP)
COST
VARIANCE
(CVAR/CV)
Task a 31/3/2024 R87000.00??? R93000-R6000
Task b 30/4/2024??? R48000 R48000-R3000
Task c 30/5/2024 R78000??? R78000???
Task d 30/6/2024 R90000 R84000??? R6000
TOTAL 30/7/2024????????????

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!